Itakpe-Ajaokuta-Warri rail line 80% completed – Amaechi (PHOTOS)

37948187_1816317105083776_2774846200917000192_n

The Minister of Transportation, Rotimi Amaechi, says that Itakpe-Ajaokuta-Warri rail project is about 80 per cent completed and will be ready soon.

Amaechi disclosed this during the inspection tour of the Itakpe-Ajaokuta-Warri rail line in Agbor.
He also stated that the rail line would be completed before the scheduled date, adding that the tracks were ready, only the stations were left to be completed.

He said: “It is between 70 to 80 per cent completed, but you must know that this job is meant to be completed in 2019.

“However, we are compelling them (the contractors) and because we are pushing them, they are working day and night to have it done.

“If it is time frame, they are well ahead of schedule. It is meant to be completed in 2019 and what we are doing here is what we are doing in Lagos-Ibadan and that project is actually a three-year contract. But we are forcing them to complete it in one-year period.

“Just like this is supposed to end by 2019 but we are saying no, you must leave site before October.
“However, we had a verbal agreement with them to quit site by June 2018.”

Amaechi stated that the government had no apology when it comes to borrowing to fund infrastructure in Nigeria.

Speaking, Fidet Okhiria, the Managing Director, Nigeria Railway Corporation, said that by September the train operation would commence to maintain the tracks.

According to him, if the government waits for all the 12 train stations to be completed, the tracks will go bad.
Okhiria said: “Technically, with the level of work now, we can run the train from Itakpe-Warri safely, the next stage is to make the convenience for passengers available which is the stations building.

“It is possible to operate now with one train, as far as we have communication signals and for the stations, some will be completed in August, some September, but we are not going to wait for that or else the tracks will go bad, so as a train operator, we will not wait.”

Chiedu Nwazojie, the Project Manager of Itakpe-Warri Railway Project, said that the project has a total of 12 stations but they are presently working on eight stations.

He said that the whole project was 302 kilometres (km), with rehabilitation ongoing 52km, which was from Itakpe to Ajaokuta, changing the wooden sleepers to concrete sleepers ones.

He said that they are working on Agenebode station, Itakpe, Eganyi, Ajaokuta, Itogbo, Uromi, Igueben-Ekhen, Igbanke and Agbor, which is the central station at the moment.

He, however, complained that the progress of work is being affected by the rainy season, stating that the initial August dateline might not be feasible.

37878738_1816317221750431_1650270574225653760_n 37890773_1816317195083767_1807481293680672768_n 37893746_1816317125083774_7129820649672933376_n 37915547_1816317318417088_7809527498034642944_n 37926808_1816317115083775_7565927080538406912_n 37931417_1816317118417108_6874398832910663680_n 37946392_1816317271750426_5249068708571119616_n 37948187_1816317105083776_2774846200917000192_n 37958598_1816317281750425_2847405189437063168_n 37971849_1816317198417100_8471432900955340800_n 37971893_1816317215083765_2601795831052894208_n

SOURCE

Comments

comments

Check Also

Murtala-Muhammed-Airport-MMA-696x372

250,975 Aircraft Passed Through Nigerian Airports In 2017 – NCAA

No fewer than 250,975 aircraft passed through 30 Nigerian airports in 2017 with majority of ...

Leave a Reply

Your email address will not be published. Required fields are marked *

Translate »